SA-3999-12 is used with Zexel and Denso injection pumps with RSV governors. Fitment depends on voltage, pump or governor mounting side, lever direction, rod geometry and travel. Similar bodies can move the lever in the wrong direction or stop short, so the installed pump and removed assembly must be reviewed together.
Item | Confirmed Information |
Product Type | Fuel shutdown solenoid |
OE / Reference Numbers | SA-3999-12 / 1752ES / SA-3999-24 |
Electrical Version | 12V and 24V versions; select by complete OE and old-unit marking |
Application Scope | Zexel and Denso injection pumps with RSV governors |
MOQ | 50 pcs |
Delivery Time | 7 - 15 Days |
Warranty | 12 Months |
Match the complete stamped reference because voltage, winding, mounting, terminals, output geometry and duty can differ within the same family.
Matching Point | Buyer Review |
Reference group | SA-3999-12 / 1752ES / SA-3999-24 |
Voltage | 12V and 24V versions; select by complete OE and old-unit marking |
Governor/pump | Zexel and Denso injection pumps with RSV governors |
Mounting side | Compare left/right position, bracket angle and hole centers. |
Lever travel | Measure resting position and the full run-to-stop movement. |
Check the electrical command, component response and final mechanical movement as separate observations. This prevents a wiring, control-module or linkage fault from being mistaken for a failed replacement part.
Observed Situation | Recommended Check |
Rod moves; engine stays running | Check stop-lever adjustment and lost motion at the linkage. |
Pulls then releases | Measure hold voltage and inspect relay or internal switching behavior. |
Movement is slow | Check voltage drop, connector resistance and lever binding. |
Coil overheats | Confirm full stroke and that the pull stage is not left energized. |
Bracket differs | Stop installation and recheck mounting side and clearance. |
Release the order only after electrical, mechanical and application evidence agrees with the removed assembly.
Approval Item | Required Information |
OE and voltage | SA-3999-12 / 1752ES / SA-3999-24; 12V and 24V versions; select by complete OE and old-unit marking |
Application | Zexel and Denso injection pumps with RSV governors |
Removed-part photos | Complete label, connector face, both mounting sides and output end |
Measurements | Hole centers, body clearance, resting output length and working travel |
Commercial details | Quantity, destination market, packing and marking requirement |
Keep the complete voltage-specific reference and old-unit marking on every order line. Similar housings do not make different coils interchangeable. Measure system voltage at the original connector during operation, then label inventory by both OE and voltage so mixed fleets cannot receive the wrong electrical version.
Use SA-3999-12 / 1752ES / SA-3999-24 as the first control, then compare the old label, voltage, connector face, mounting-hole centers, output end and operating direction. Record the engine or machine model and serial number, but do not use the model name alone because production changes can introduce another shutdown arrangement.
RSV/KRT-style installations can use different bracket sides and lever directions. A correct-voltage unit may still pull away from the stop position or sit outside available clearance. Send a pump-side installed photo, bracket dimensions and lever direction before technical approval.
The solenoid may complete its own stroke while free play or incorrect adjustment prevents the injection-pump lever from reaching stop. Watch the lever, not only the rod, and check pivots, linkage length, bracket flex and the mechanical stop.
No. The governor family is useful context, while voltage, mounting side, bracket spacing, rod thread and required travel establish interchangeability. Compare the complete OE group and removed assembly because neighboring pump families can use visually similar but mechanically different kits.
Compare the full label, voltage, connector face, terminal count, mounting-hole centers, body orientation, output end, resting length and working travel. Include one wider installed photo showing pump, lever or surrounding clearance because close product images can hide the geometry that decides fitment.
Correct the original failure cause before installation. Check supply voltage, pull/hold timing, linkage resistance, mechanical stops, terminal tightness, heat and moisture exposure. A new unit can fail quickly when the high-current stage remains energized or the output cannot complete its designed stroke.
Send the complete reference group, confirmed voltage, Zexel and Denso injection pumps with RSV governors, removed-part photos, measurements and order quantity for a fitment-focused B2B quotation.